99
1.Quote | According to samples, designs and specific requests |
2.Discussion | Mould material, cavity number, runner, price, payment |
3.Purchase order | Approval for all items |
4.Advance | 40% deposit with P.O by TT |
5.Mould Design Checking | We make mould designs on the basis of confirmed product design, and send to customer for confirmations |
6.Mould Processing | Send report to customer each week |
7.Mould Testing | Send trial samples and try-out report to customer for confirmation |
8.Mould Modification | According to customer's feedback |
9.Balance Settlement | Mid term (first shot) 40%, final term (upon approval before shipping) 20% |
10.Delivery | By sea or by air, as your requirement |